Thursday, May 30, 2013

Two Weeks Until Go Live

I have been too busy to post- we sailed through integration testing but hit a snag with website preparedness.
SAP stepped up and dedicated staff to fix bugs- the patch we received did not do the trick and we are now waiting for another patch.
It's all about WCEM3 at this point.  We are almost ready to go live but still have so much work to do.

We pushed go live out by 2 weeks, and still people are starting to panic that we don't have enough time.

I keep pushing for the goal!

Friday, April 19, 2013

PB3 Almost Complete

Great week- still have financial close on Monday which will officially end PB3.

Very tense times.  We did a good job but also know there is much to do.

Wednesday, April 10, 2013

Week 20

We are prepping for playback 3.  All is on time and on budget at this point.  My biggest surprise has been how as project sponsor I spend so much of my time listening to complaints and coaching people on how to work together as a team.

Monday, March 18, 2013

PB2

We completed play back 2 last week.  It was a huge success.  We are still on track. We have 5 consulting groups on the project and all of them seem committed to getting this done on time and on budget.
Amazing week.  I was really proud of my team.  They drove the demos and really pushed to get what ever they need to make sure thier sessions were a success.

Friday, March 1, 2013

Change Orders- Learnings

One thing I have learned in a project of this size, instead of just creating a 7% contingency into the bottom line of the overall budget I should also have anticipated perhaps a 5% change order contingency directly related to each SOW.

Thursday, February 28, 2013

Prepping for PB2

We had a team building event last night and it went well.  We are a week away from PB2 and tensions are high.  I am dealing daily with concerns about consultants, requirements and increased costs.  That said, we are still within our budget (while using contingency funds).

Tuesday, February 12, 2013

SAP Implementation

I am in the middle of an SAP implementation project.  Week 13 of a 33 week accelerated roll out.  I started this blog as a diary on another site because I wanted total anonymity but that site is not available so I will start over today.

We are right on track with timeline and budget.  We went through Blue Printing and then Design Doc sign off.  Now we are in PB1.  Day 2 was very successful.