Tuesday, February 12, 2013

SAP Implementation

I am in the middle of an SAP implementation project.  Week 13 of a 33 week accelerated roll out.  I started this blog as a diary on another site because I wanted total anonymity but that site is not available so I will start over today.

We are right on track with timeline and budget.  We went through Blue Printing and then Design Doc sign off.  Now we are in PB1.  Day 2 was very successful.

No comments: