Thursday, February 28, 2013
Prepping for PB2
We had a team building event last night and it went well. We are a week away from PB2 and tensions are high. I am dealing daily with concerns about consultants, requirements and increased costs. That said, we are still within our budget (while using contingency funds).
Tuesday, February 12, 2013
SAP Implementation
I am in the middle of an SAP implementation project. Week 13 of a 33 week accelerated roll out. I started this blog as a diary on another site because I wanted total anonymity but that site is not available so I will start over today.
We are right on track with timeline and budget. We went through Blue Printing and then Design Doc sign off. Now we are in PB1. Day 2 was very successful.
We are right on track with timeline and budget. We went through Blue Printing and then Design Doc sign off. Now we are in PB1. Day 2 was very successful.